Project Portfolio
Gas Distribution Projects
Southern California Gas Company: Blanket contract for Metropolitan Los Angeles 2011-2014, 10-12 crews, time & material, unit prices. Reference – Lisa Wang, SCG Procurement, 213-244-5384.
Southern California Gas Company: Install 15,000 feet of 6" steel gas pipeline and 7,000 feet of 6" plastic gas pipeline in the City of Palm Desert. Reference – Cody Kuezada, SCG Ops, 760-535-5332.
Southern California Gas Company: Install 4,600 feet of 8" steel gas pipeline in the City of Palm Springs. Reference – Cody Kuezada, SCG Ops, 760-535-5332.
Transmission Pipeline Projects
Southern California Gas Company: Install 750 feet of 36" steel gas pipeline in the City of Palm Springs. Reference – Tim Pearce, SCG Ops, 951-440-4966
Airport Fuel Distribution Projects
Los Angeles International Airport: Install 1,580 feet of 20", 4480 feet of 18", 2240 feet of 16", 2730 feet of 14", and 1000 feet of 6" jet fuel pipeline. Install 30 hydrant pits, 16 low point drains, and 5 high point vents. Reference – Dan Sparks, Flatiron Construction, 619-572-2519
Sacramento International Airport: Install 1160 feet of 14", 4600 feet of 10", and 1000 feet of 6" aircraft fuel pipeline. Install 25 hydrant valve pits, 5 low point drains, 4 low/high point pits and 2 high point pits. Reference - Alesander Romo, Turner Construction, 916-874-0280
Oakland International Airport: Adjust existing fuel hydrant pits and low point drains. Adjust existing IVP's and CP test stations. Install 3 hydrant pits, 125 feet of 6" aircraft fuel pipe and 138 feet of 10" aircraft fuel pipe. Reference - Zack Petit, Gallagher and Burke, 510-821-4271
Sky Harbor International Airport: Excavate and exposing 10" line, removal of existing coating, Installation of repair sleeve/s, repair coating and backfilling of 10 areas of external corrosion in 8 different locations. Reference – Dan Liss, Swissport, (602) 275-3047